Construction Updates

Print
Press Enter to show all options, press Tab go to next option

Construction Update   Wednesday, September 5, 2019

  • Chip Seal - 9/5/19 Under traffic with single lane closures
  • CTH S Bridge (Edge) 
  • CTH Y Bridge (Jim Falls)

 

Construction:

  •  CTH Q (CTH B (west)- CTH C)
  • Pipe liners and minor drainage work started last week
  • Milling asphalt & paving 1.3 miles, open to local traffic. Work on the road surface will not occur until after the Tilden Shin Dig on July 21st.
  • CTH X (184th St. – CTH K) Currently in progress
  • Concrete median at 190th St. removed
  • Mill and overlay of asphalt surface

 

Bridge & Culverts:

  •  CTH F (CTH B - CTH Q) Closures starting 9/10/19
  • Culvert replacements/ lining
  • Detour will be used for extended closures