Construction Updates

Print
Press Enter to show all options, press Tab go to next option

Updated September 19, 2018

HIGHWAY & BRIDGE SCHEDULE REPORT – FALL 2018

Chippewa County’s list of 2018 highway construction and maintenance projects is shown below.  Please note that these dates are approximate and actual construction timeframes are subject to change.

 

2018 Construction Projects:

CTH UN (CTH P – 160th St.)  

  • Paving 2 miles with some roadway realignment

  • Update:  All work has been completed

CTH M (STH 27 – CTH G North)

  • Paving 5 miles

  • Update:  All work has been completed

CTH H (30th Ave – County Line)

  • Reconstruct 2 miles, closed to traffic during portions of project

  • Update:  Ditch and culvert repairs due to flooding have been completed.  The remaining surface layer of asphalt paving is scheduled to be completed within the next week.  Shouldering and pavement markings will follow paving.

 

Culvert Replacements for 2019 Paving Projects:

CTH M (275th Ave – Taylor County Line)

  • Culvert replacements will take approximately 3 weeks

  • Update:  Remaining culvert installations will be completed this week.

CTH Q (CTH B – CTH C)

  • Drainage and culvert replacements will take approximately 2 weeks

  • Tentatively scheduled for late-September

 

2018 Bridge Projects:

CTH K Bridge (Little Drywood Creek) 

  • Update:  Larson Construction is preparing to pour the bridge deck slab in the next few days, weather permitting.

  • The highway is closed with no posted detour.

 

2018 Maintenance Projects:

Chip Seal:

  • CTH SS (Bloomer City Limits – STH 40) 1.0 mile – complete
  • CTH O (Lake Wissota State Park – CTH K) 2.0 miles – complete

Bridge Deck Rehabilitation and Chip Seal:

  • CTH M – Lake Holcombe Bridge ( “Blue Bridge”)
    • Update:  No bridge deck repairs needed, chipseal work completed
  • CTH O – Yellow River Bridge
    • Update:  Bridge deck repairs completed, chipseal work completed
  • CTH S – Chippewa River Bridge (near The Edge)
    • Update:  Bridge deck repairs completed, chipseal work completed
  • CTH XX – Yellow River Bridge
    • Update:  Bridge deck repairs completed, chipseal work completed
  • CTH Y – Chippewa River Bridge (Jim Falls)
    • Update:  Scheduled for 2019