Construction Updates

Print
Press Enter to show all options, press Tab go to next option

Updated June 20, 2018

HIGHWAY & BRIDGE SCHEDULE REPORT – Summer 2018

Chippewa County’s list of 2018 highway construction and maintenance projects is shown below.  Please note that these dates are approximate and actual construction timeframes are subject to change.

2018 Construction Projects:

CTH UN (CTH P – 160th St.)  

  • Paving 2 miles with some roadway realignment, open to local traffic only
  • Update:Project started on May 15th and is expected to continue for 8-10 weeks

CTH M (STH 27 – CTH G North)

  • Paving 5 miles, open to local traffic only
  • Update:Paving expected to begin on May 21st and continue for 10 working days

CTH H (30th Ave – County Line)

  • Reconstruct 2 miles, closed to traffic during portions of project
  • Update:Antczak Construction has begun grading construction and is scheduled to finish in early-August
  • Chippewa County will pave once completed

 

Culvert Replacements for 2019 Paving Projects:

CTH M (275th Ave – Taylor County Line)

  • Culvert replacements 3 weeks
  • Tentatively scheduled for July

CTH Q (CTH B – CTH C)

  • Drainage and culvert replacements 2 weeks
  • Tentatively scheduled for August

 

2018 Bridge Projects:

CTH K Bridge (Little Drywood Creek) 

  • Contractor starting in summer, 2 month duration.
  • Road closed, no posted detour

 

2018 Maintenance Projects:

Chip Seal work for the week of August 27th:

  • CTH SS (Bloomer City Limits – STH 40) 1.0 mile
  • CTH O (Lake Wissota State Park – CTH K) 2.0 miles

Bridge Deck Rehabilitation and Chip Seal:

  • CTH M – Lake Holcombe Bridge ( “Blue Bridge”)
    • Chipseal only
  • CTH O – Yellow River Bridge
    • Update:  Bridge deck repairs in progress
  • CTH S – Chippewa River Bridge (near The Edge)
    • Update:  Bridge deck repairs completed
  • CTH XX – Yellow River Bridge
    • Update:  Bridge deck repairs completed
  • CTH Y – Chippewa River Bridge (Jim Falls)
    • Update:  Scheduled for 2019